If 70 men dig 15,000 sq. m of a field in 5 days how many men will dig 22,500 sq. m field in 25 days ?

0 votes
1 view
asked May 15 in Class VIII Maths by aditya23 (-1,696 points)

If 70 men dig 15,000 sq. m of a field in 5 days, how many men will dig 22,500 sq. m field in 25 days ?

Please log in or register to answer this question.

1 Answer

0 votes
answered May 15 by muskan15 (-3,360 points)

70 men dig 15,000 sq. m of a field in 5 days

1 men can dig 15,000 sq. m of a field in = (5 × 70)/15,000

Men required to dig 22,500 sq. m field in 25 days = (5 × 70 × 22500)/(15,000 × 25) = (70 × 900)/3000 = 63/3 = 21

Hence required to dig 22,500 sq. m field in 25 days = 21