A can do \frac { 1 }{ 4 } of a work in 5 days and B can do \frac { 1 }{ 3 } of the same work in 10 days.

0 votes
1 view
asked May 15 in Class VIII Maths by priya12 (-11,279 points)

A can do 1/4 of a work in 5 days and B can do 1/3 of the same work in 10 days. Find the number of days in which both working together will complete the work.

Please log in or register to answer this question.

1 Answer

0 votes
answered May 15 by navnit40 (-2,750 points)

A can do ¼ of work in = 5 days

A can do 1 work in = 5 × 4 days

= 20 days

B can do 1/3 of work in = 10 days

B can do 1 work in = 10 × 3 days

= 30 days

A’s 1 day work = 1/20

B’s 1 day work = 1/30

(A + B)’s 1 day work = (1/20) + (1/30)

= (3 + 2)/60

= 5/60

= 1/12

∴ A and B working together will complete the work in = 12 days